The St. Vrain Greenway Is Crossing Highway 119: Where Longmont's Eastern Trail Stands This Winter

November 5, 2026

For about eight miles, the St. Vrain Greenway follows the creek from Golden Ponds Nature Area east to Sandstone Ranch, and then it stops. St. Vrain State Park sits a little more than two miles farther northeast along the same creek corridor. Longmont adopted a plan to carry the trail along St. Vrain Creek toward Boulder Creek back in 2001.

Colorado Highway 119 runs between the trail's end and the park, so almost every milestone on the eastern extension this year has been a highway milestone. The next one comes overnight on Monday, Nov. 16.

Where the eight miles end today

The city calls the project St. Vrain Greenway Phase 13, the Eastern Extension. The new trail starts at the driveway and parking area west of the Sandstone Ranch Visitors Center and runs more than two miles to the trail network at St. Vrain State Park. It will be 10 feet wide.

The connection goes well beyond Longmont. Phase 13 is designed to link eventually with the Weld Legacy Trail east of I-25 in Firestone, and the St. Vrain Greenway is part of the Colorado Front Range Trail, which is planned to run from Wyoming to New Mexico. Today all of that depends on getting people on foot and on bikes safely across the Diagonal near County Road 5½.

Why a two-mile trail needed a highway work zone

The project includes two pedestrian bridges. One sits north of CO 119 over St. Vrain Creek, and the other sits south of the highway overlooking the creek. A concrete underpass beneath the highway connects them. Building an underpass under a working state highway means moving traffic out of the way in stages, and drivers on the Diagonal have been doing that since spring:

When What changed on CO 119
Week of March 23, 2026 Phase 1 pattern: eastbound traffic moved to the right shoulder, westbound into temporary center lanes, 45 mph work zone
Aug. 11, 2026 Phase 2 pattern: westbound on the outside shoulder, eastbound in temporary center lanes, concrete barriers between them
Oct. 18–19, 2026 Phase 3 transition: traffic moved out of the head-to-head setup and back to its normal configuration

When the city announced the Phase 2 pattern in late July, it said that layout would stay through the winter while crews built the underpass. Instead, traffic went back to normal in mid-October. Some shoulder closures remain in place, and the acceleration lane near CR 5½ stays closed. Through the first two phases, two lanes stayed open in each direction.

The Nov. 16 lift

The City of Longmont's notice sets the overnight work from 6 p.m. Monday, Nov. 16, to 7 a.m. Tuesday, Nov. 17, on westbound CO 119 between CR 7 and CR 5½. Crews will assemble the bridge sections and lift the structure into place with cranes, and the city expects the installation to take one night. Drivers heading west toward Boulder that evening should expect a temporary right-lane closure near CR 5½, with construction trucks entering and leaving the work zone.

The city calls this the project's second pedestrian bridge. Its September update scheduled a bridge installation for Thursday, Sept. 24, using five prefabricated sections and a crane over roughly five hours. That work required no closures on CO 119 or County Road 5. The November structure is the one that needs the highway lane closed while it goes up.

What still stands between Sandstone Ranch and the state park

Once the second bridge is up, the work left is the finishing work on the crossing. The city's Phase 3 list includes:

  • Guardrail and pedestrian railing installation
  • Stone veneer and wall fascia work
  • Embankment work
  • The sidewalk extension and connection at County Road 5½

The city's schedule runs construction from January 2026 to spring 2027, and its construction-start announcement put the finish in April 2027.

Closer to home, regular Sandstone Ranch visitors have been working around a smaller change since last December. Starting Dec. 23, 2025, part of the Sandstone Ranch Parking Area near the Visitors Center closed for the duration of the project. Trails and the Visitors Center stay open, and extra parking is available at the Visitors Center and the Sandstone Soccer Complex. Sandstone Drive has also closed briefly several times for concrete curing, most recently Aug. 31 through Sept. 4. During those closures, the park and the greenway stayed reachable from the main parking area and the soccer field lots.

One thing will come later. The city plans interpretive signs along this segment in a future phase, with locations still to be chosen.

What waits at the far end

St. Vrain State Park is run by Colorado Parks and Wildlife, so the greenway's new endpoint has a gate fee. CPW's fee table lists a $4 individual daily pass for anyone entering on foot or by bicycle. A one-day vehicle pass for Colorado plates costs $10 to $12. Once the trail opens, a family arriving by bike will pay per person, not per car.

The park has construction of its own this fall. CPW says a paving project closed the south campground access road as of Oct. 13, so full-hookup sites 42 through 87 are unavailable. Trails on the south and east sides of Bald Eagle and Coot Ponds and all of Red Tail Pond are closed through November, possibly into December 2026. Check CPW's closure notice before driving out for a pond loop this month.

The rest of the Diagonal runs on the same calendar

Phase 13 is the eastern piece of a larger rebuild of the road it crosses. The CO 119 Safety, Mobility and Bikeway project covers the Diagonal from roughly Foothills Parkway in Boulder to Hover Street in Longmont. It is a $165 million program built by Kraemer North America, with a CDOT timeline from fall 2024 to spring 2027. CDOT, RTD and Boulder County are partners, with Longmont and Boulder also taking part. The work pairs bus rapid transit and intersection safety improvements with a nine-mile paved bikeway. Boulder County expects completion in January 2027.

That puts the Boulder bikeway and the eastern greenway extension on track to finish within a few months of each other. The 2001 trail plan never could have counted on that timing.

The Hover Street end will take longer. CDOT's CO 119 and Hover intersection project runs from April 2026 to December 2027. Its design includes a Boulder-bound overpass and trail connections. CDOT says all left turns there are closed during construction, along with the right turn from southbound Hover onto southbound CO 119. Business access is maintained, and the closures last until late 2027.

The intersection also holds up a smaller amenity. Longmont's BCycle e-bike share opened this summer with about 30 pedal-assist bikes at five docks: 6th and Coffman, the 8th and Coffman RTD Park-n-Ride, the Longmont Public Library at 350 Kimbark St., the Longmont Recreation Center at 310 Quail Rd., and Rogers Grove Nature Area at 220 Hover St. The city has said a sixth dock will go in at Hover Street and CO 119 once construction in that area is complete.

The greenway's other unfinished end is further out. Phase 12, the western extension from the current terminus toward Boulder County land west of Airport Road, lists funding restoration as anticipated to begin in 2026. Design and bidding are still ahead, and construction is projected for 2027 through 2029. The eastern gap is the one closing first. Phase 13 is partially funded by a Denver Regional Council of Governments Multimodal Options Fund grant administered by CDOT.

For now, the plan is simple. Park at the Sandstone Soccer Complex if the Visitors Center lot is full, give the Diagonal near CR 5½ extra time on the night of Nov. 16, and plan on spring 2027 for a ride from Golden Ponds to the state park gate.

Our family has watched Longmont's trail map grow one phase at a time for decades. If you live near Sandstone Ranch or along the Diagonal and wonder how a finished greenway connection and a rebuilt CO 119 could affect what your home is worth, The Mock Group is glad to talk it through. Request a home valuation, and we'll walk you through what's changing on your side of town.