At Sloan's Lake, the Shoreline Gets Rebuilt Before the Lake Does

November 12, 2026

Sloan's Lake used to be 8 to 12 feet deep. Today it is closer to 2.5 to 3 feet, according to The Colorado Sun. That is shallow enough that about 2 million visitors a year walk dogs, fish and paddle around a 2.6-mile loop whose water heats up quickly in a Denver summer.

The city's answer is a proposed $50 million dredging project, announced Sept. 2. That headline sets the wrong expectation for this winter. Over the next year, the work you will see happens on land: a parking lot in the southwest corner, the courts on the north side, and the old boathouse near the marina. In the city's sequence, the lake comes last.

Why the water is the hard part

Stormwater has carried sediment into Sloan's Lake for decades. That has made the lake shallower and warmer, and it has made the water easier for algae to take over. In 2024, several days near 100 degrees set off a bloom that used up the oxygen fish needed. The city pumped in cold water to save them, but more than 2,000 carp and crappie died. The Colorado Sun reported a similar die-off in 2020.

Shallow water also makes the lake less drought-tolerant and less able to absorb stormwater, the city said in its announcement. The city has already reshaped some of the shoreline and installed aerators, Denverite reported. Denverite called those minor improvements.

Because depth is the core problem, the real fix requires taking sediment out of the lakebed. Getting that done takes approvals, permits and a construction window. Rebuilding a parking lot takes far less of each, so the land projects come first.

The loop, project by project

Denver Parks and Recreation keeps one project page for the Sloan's Lake neighborhood. Here is what it lists, in the order you would reach each spot on the loop:

  • Southwest corner, Sheridan Boulevard and 17th Avenue. The parking lot and basketball court here were scheduled to close in September 2026 while the nearby building becomes a maintenance facility for northwest Denver parks. Later in construction, part of the trail will close too. The city expects the closures to last through early 2027 and asks people to follow posted detours.
  • North side courts. The tennis and basketball courts on the north side are being replaced and made more accessible. The schedule calls for construction to start in winter 2026 and finish in fall 2027. DPR Capital Funds and the RISE Denver Bond are paying for it.
  • The boathouse, near Wolff Street and West Byron Place. Parks Operations, Adaptive Recreation and the Park Rangers use the historic building now. The plan turns it into a 2,500 to 3,000 square foot community and event space connected to the marina, and it will still support park operations.
  • South playground and tennis courts. These are already finished. That project wrapped up in October 2023.

The south playground is the only finished piece. Every other project ahead of the dredging is on the north and west edges of the park.

A boathouse built for gatherings

Of the land projects, the boathouse will change the most about how the park gets used. In February, Denverite described the plan as a 171-person event space with a catering kitchen and a concession stand, with rentals run by the city. At that point, the renovation was expected to cost about $7 million and could open in winter 2028.

The design came out of three rounds of public input: a meeting on July 29, 2025, a virtual meeting on Sept. 18, 2025, and an open house on Jan. 29, 2026, where the design team showed the preferred concept.

A boathouse on a shallow lake has an obvious limit. The building can get a new kitchen and a rental calendar. The marina beside it still depends on how deep the water is.

The lake's own timeline

Project Where Scheduled timing Paid for by
Maintenance yard and lot closure Sheridan Blvd. and 17th Ave. Sept. 2026 through early 2027 Not specified on the city page
North tennis and basketball courts North side Winter 2026 start, fall 2027 finish DPR Capital Funds, RISE Denver Bond
Boathouse event space Wolff St. and W. Byron Pl. Possible winter 2028 opening, as reported in Feb. 2026 About $7 million
Lake dredging and shoreline restoration The lake itself Permitting 2027, work starting 2028 Up to $40M St. Anthony urban redevelopment area, $5M Vibrant Denver bond, $5M wastewater fund

The last row has the biggest price tag and the latest start. The proposal would deepen the lake, try to keep new sediment from building up, and restore the shoreline. The largest share of the money comes from the St. Anthony Urban Redevelopment Area. That district was created in 2013 to revitalize the Sloan's Lake area after St. Anthony Central Hospital moved to Lakewood. Denver voters approved $5 million through the Vibrant Denver Bond, and the city's wastewater fund covers another $5 million. The city says the funding will not raise taxes or affect its budget.

Mayor Mike Johnston told Denverite the redevelopment district had been "so successful ahead of schedule that we have additional dollars we can allocate."

The proposal needs approval from both the Denver Urban Renewal Authority board and the Denver City Council. The authority's Sept. 14 special meeting agenda included a resolution titled "Approval of Commitment of Funds for Project in the St Anthony Urban Redevelopment Area." Once approved, the city aims to finish permitting in 2027 and start work in 2028, The Colorado Sun reported. Dredging and the related improvements are expected to take 30 months once they begin. Thirty months from a 2028 start runs into 2030.

Parks director Jolon Clark described the near term plainly. "There are still some approvals that need to happen before anything starts to move forward," he told Denverite. "So in the very short term, not a lot of changes, but the focus throughout the project will be to keep as much of the park open and usable as possible, doing work in the lake."

Who is waiting on deeper water

The shallow water already affects the park's biggest event. The Colorado Dragon Boat Festival held its 2026 edition at Sloan's Lake on Aug. 29 and 30, with no on-site parking. Festival-goers were directed to shuttles, bike corrals and outside lots. Festival organizers attended the mayor's announcement. Denverite reported that the festival has had trouble in recent years finding routes deep enough for the boats.

Edgewater Mayor Steve Conklin also welcomed the news. The town sits just west of the park, and Denverite noted that its nearby commercial areas depend heavily on park visitors. Councilwoman Amanda Sandoval, quoted in The Colorado Sun, said the work would keep the lake "a jewel of North Denver for the next seven generations."

Kurt Weaver, executive director of the Sloan's Lake Park Foundation, has pushed for investment at the lake for five years. He told Denverite the dredging project could let the foundation become a "Friends of the Park" group focused on smaller needs. "Can we plant some more trees? Do we need more benches? Are the soccer fields upkept?"

Weaver's list sets the order for the next few years. Benches, trees and fields come after the lake is fixed. This winter, the scheduled work is at the Sheridan and 17th lot and the north courts, while the dredging waits on approvals and permits.

Our family has watched Front Range parks get rebuilt for three generations, and a project schedule like this one tells you a lot about a neighborhood's next few years. If you own near Sloan's Lake and want to know how the boathouse, the courts and a planned lake restoration fit into what your home is worth, The Mock Group can walk through it with you. Request a home valuation and we'll start there.