Superior Colorado Community Center Reopening and Winter Plans

October 29, 2026

At 3300 Huron Peak Avenue, the South Pool is an open hole in the ground. Its deck is gone, and crews are digging out the new basin and laying underdrains. A few miles north at 1650 S. Indiana Street, the North Pool's deck and bathhouse interior are nearly demolished. Xcel was scheduled to pull the old transformer there the week of Oct. 26. On Coalton Road, the Superior Community Center has its new asphalt down, and staff were set to move back in before the end of October.

Superior shut several shared places at the same time this year. They are reopening on two very different schedules. The road and the Community Center come back in the first half of November. Both pools stay closed through the winter. Between now and May, Superior's public calendar runs through a small number of addresses: 1500 Coalton Road and the 2250 block of Main Street.

Friday: Rock Creek Parkway is due back

The street comes first. The Town says crews are working toward "substantial completion" of the Rock Creek Parkway reconstruction between Enterprise Street and Coalton Road by Friday, Nov. 6. That will end a summer and fall of lane closures. Crews finished the northbound side first, then moved to the southbound lanes in October.

The road will look different when it's done. New raised crosswalks and islands are finished on the northwest and northeast corners at Coal Creek Drive. At Coalton Road, the northeast corner has a raised crosswalk, a new curb ramp, and a concrete "pork chop" island. Honey Creek Drive was repaved on Oct. 22. The top layer of asphalt on Rock Creek Parkway was scheduled for Oct. 26 and the overlay at the Coalton intersection for Oct. 27, with striping to follow.

If you ride transit, this part matters most. While the southbound lanes have been closed, the southbound RTD 228A stops at Rock Creek Village/Bell Flatirons and at Honey Creek Drive have been closed too. The Town says all of this work depends on the weather. Its interactive road construction map shows closures and detours in detail, so check it before counting on those stops.

Around Nov. 9: The Community Center reopens a few days later than first planned

The Superior Community Center at 1500 Coalton Road closed on Aug. 3. The repairs weren't cosmetic. The Town described them as fixes for "drainage and foundation concerns." When the closure was announced in July, the Town's FAQ said the building was "expected to reopen during the first week of November 2026." The latest update moves that a few days:

"The building will likely open to the public again on or around Nov. 9."

That line comes from the Town's Weekly Happenings newsletter for Oct. 26 to Nov. 1. The same update says the concrete work is done, including curb and gutter, a new west patio, a new ADA parking space, and valley pans for drainage. Paving is finished too. Landscape restoration, striping, cleaning, and a final punch-list walk were scheduled before the doors open.

Here's what the reopening ends. For three months, the Community Center library locker has been unavailable, and the Town pointed borrowers to the Louisville Library at 951 Spruce St. or to the 24-hour drop box outside Superior Town Hall at 124 E. Coal Creek Drive. Programs and room reservations moved to the Superior Civic Space at 2250 Main St., Suite 1001. Questions about specific programs go to the Guest Service Associates at 303-554-9005.

The first big event back in the building comes about four weeks after the estimated reopening. The 6th Annual Superior Holiday Bazaar fills the Community Center on Saturday, Dec. 5, from 10 a.m. to 3 p.m., with more than 50 vendors selling holiday arts, crafts, food, and gifts. "Bumble" the Yeti Snowman will be there for photos. Part of the vendor sales goes to the Superior Khandbari Sister City partnership with Khandbari, Nepal. The reopening date is still an estimate, but even with another short slip, the building would be open well before the bazaar.

May 2027: Both pools are closed at once

The pools are where this year's calendar really splits. The Town is rebuilding both at the same time, and both have the same target: a "scheduled reopening date in May 2027."

North Pool's last day of the 2026 season was Sunday, Aug. 23. The Town's contractor, A.D. Miller, started work the next morning. The pool is older than many people assume. It was built more than 30 years ago as part of Superior Metropolitan Districts 2 and 3, the Town took it over in 2004, and it holds 165,000 gallons across eight lanes.

North Pool South Pool
Address 1650 S. Indiana St. 3300 Huron Peak Ave.
What's new New pool shell and deck, updated bathhouse, more shade, zero-depth-entry wading pool, more efficient mechanical and sanitation systems Larger pool, renovated bathhouse, 25-foot slide, current channel, splash pad, upgraded mechanical systems
Budget $5.27 million $4.65 million total
Funding listed in the 2026 budget Bond proceeds project Government capital
Target reopening May 2027 May 2027

Both are being done now because of a 2024 vote. In November 2024, voters approved a 0.315% sales and use tax for capital projects. The Town issued bonds in 2025 to start projects sooner and plans to use the new tax revenue to pay off that debt, according to the 2026 final budget. That same budget document had shown South Pool construction in 2027 and 2028. The work started this fall instead.

Until spring, both sites come with some daily friction. At North Pool, the tennis courts stay open, a few parking spaces near the lot entrance are held for players, and a marked walking route runs along the construction fence. The North Pool lot can't be used for school drop-off during construction. At South Pool, the playground closes on and off during concrete demolition, and the Town says it will post signs when the area is safe again.

Where the winter calendar actually is

With both pools fenced, almost every public event on the calendar between now and the end of the year is at one of two places: the reopened Community Center on Coalton Road, or Downtown Superior along Main Street. The Superior Civic Space at 2250 Main St. hosted the Community Center's programs all fall and now has a winter schedule of its own.

The dates that hold up on the Town's own pages:

  • Friday, Nov. 20, 6 p.m. Boulder Film Friends screens "The Best Christmas Pageant Ever" at the Superior Civic Space, 2250 Main St. Free.
  • Saturday, Dec. 5, 10 a.m. to 3 p.m. The Holiday Bazaar at the Community Center, 1500 Coalton Road.
  • Saturday, Dec. 12, 2 to 5 p.m. The free Winter Festival at Downtown Superior, 2250 Main St., with Santa photos, live performances, hot chocolate, and shopping.

Downtown also has a new way to get around this season. BCycle e-bike share came to Superior this fall with 20 Class 1 electric-assist bikes and 38 docks. Stations are at Founders Park, Community Park, Superior Civic Space, and Superior Commons Park. The Town's BCycle announcement says riders must be at least 18. Superior's system is part of a regional partnership led by the City of Longmont and funded through the Colorado Energy Office's Community Accelerated Mobility Project grant. Boulder County, Broomfield, Lafayette, and Westminster are also in it, and the plan is for riders to pick up and drop off bikes across participating communities as the network grows.

Some of downtown is still being built. bb.q Chicken has kitchen equipment on site and its sound-isolation system going in. In a note shared in the Town's September 2026 Downtown Superior bulletin, the owners mentioned material delays and said they look forward to welcoming the community "over the coming months" for Korean fried chicken and a full-service bar. At the Foxley project, the south building's exterior is complete. The north building is targeted for "next summer," a projection from the Town's October 2026 Downtown Superior bulletin, which was published in early September.

The road is due back Nov. 6, the Community Center around Nov. 9, both pools in May 2027, and the Foxley north building sometime next summer. Until the pools reopen, the town's shared calendar runs through Coalton Road and Main Street. The Town notes that its schedule can change, and the Town Projects page posts dated updates as each project moves.

At The Mock Group, we follow Superior's projects date by date because they shape how people in town spend their week, and over time they also show up in how a home's location reads to buyers. If you're wondering how a rebuilt pool, a finished road, or new pieces of downtown might figure into your own home's value, request a home valuation and we'll go through it with you.